Update #2 - Crestview Water System Improvements
Following maintenance work on the Kathleen Road watermain, Kathleen Road is now open for traffic.
Regular service on bus routes 201 and 202 has resumed.
New watermains were installed and put into service crossing Azure (near the pumphouse), along Rainbow, Minto, and Kathleen Roads. Curb, gutter, sidewalk, and road paving are also nearly complete in these areas.
Route 201 and 202 buses have returned to their regular service in Crestview.
Remaining work will not impact vehicle or transit traffic. It includes:
- Watermain connections or capping along Squanga Avenue at Rainbow, Kusawa, and Dezadeash Roads
- Concrete curb and asphalt patching
Thank you for your contribution!